Delay in requests clause: Copy, customize, and use instantly

Introduction

The delay in requests clause outlines the responsibilities of the parties when there are delays in fulfilling requests or obligations under the agreement. It specifies the procedure for notifying delays, potential consequences, and any exceptions to the general delay provisions, ensuring that both parties are aware of how delays will be managed.

Below are templates for delay in requests clauses tailored to different scenarios. Copy, customize, and insert them into your agreement.

Standard delay in requests clause

This variation applies when a delay occurs due to circumstances within the control of the party.

If either party experiences a delay in fulfilling any request or obligation under this agreement, they must notify the other party in writing as soon as possible. The notification must include the reason for the delay, the expected duration of the delay, and any steps being taken to mitigate the impact. Delays that exceed [X] days may result in a breach of the agreement unless otherwise agreed by both parties.

Delay due to force majeure clause

This variation applies when a delay is caused by force majeure events.

Neither party shall be held responsible for delays in fulfilling requests or obligations under this agreement due to force majeure events such as natural disasters, acts of war, strikes, or government restrictions. The affected party shall promptly notify the other party of the occurrence of such an event and the expected duration of the delay. In the event of a prolonged delay, both parties will work together to agree on an alternative timeline or resolution.

Consequences of delay clause

This variation applies when specifying the consequences of delays.

If either party delays the fulfillment of a request or obligation under this agreement without justifiable cause, the other party may seek remedies including but not limited to a reduction in the agreed payment, extension of deadlines, or termination of the agreement. Both parties acknowledge that time is of the essence for this agreement and any delays may result in operational impacts.

Extended delay clause

This variation applies when extending timelines due to delays.

In the event that a delay in fulfilling a request or obligation under this agreement exceeds [X] days, both parties agree to renegotiate the timeline or extend the deadline for performance by a mutually agreed period. Any such extension will be documented in writing and signed by both parties.

Delay notification clause

This variation applies when outlining the requirement to notify the other party of a delay.

If either party anticipates a delay in fulfilling any request or obligation under this agreement, they shall notify the other party in writing within [X] days of identifying the delay. The notification should specify the cause of the delay, an updated timeline, and any mitigation measures being implemented.

No delay clause

This variation applies when specifying that delays are not acceptable.

Both parties agree that any delay in fulfilling obligations under this agreement shall be considered a breach of contract, unless caused by circumstances beyond their reasonable control. In the event of a delay, the non-delaying party may pursue remedies available under law, including seeking compensation for damages or terminating the agreement.

Delay due to regulatory issues clause

This variation applies when a delay is caused by regulatory or legal issues.

If a delay in fulfilling any request or obligation arises due to regulatory, legal, or compliance-related issues, the affected party will notify the other party as soon as possible. The delay will be excused to the extent that it is directly caused by such issues, but both parties agree to work together to resolve the issues promptly and minimize any disruption to the performance of the agreement.

Delay in third-party performance clause

This variation applies when a delay occurs due to third-party involvement.

If any third party engaged by either party causes a delay in fulfilling a request or obligation under this agreement, the party experiencing the delay will promptly notify the other party. The affected party agrees to take reasonable steps to expedite the third-party’s performance or seek an alternative third-party solution, and both parties agree to discuss any necessary adjustments to the timeline.

Delay due to internal processes clause

This variation applies when delays are due to internal processes of a party.

If a delay in fulfilling any request or obligation arises due to internal processes within [Party Name], the affected party must inform the other party in writing and provide a clear explanation. The parties agree to work collaboratively to resolve any internal bottlenecks or delays, ensuring minimal impact on the performance of the agreement.

Partial delay clause

This variation applies when only part of the request or obligation is delayed.

If only part of the request or obligation is delayed, the non-delaying party may proceed with the parts of the agreement that can be fulfilled on time. Any delayed portions will be addressed as soon as possible, and the affected party will provide an updated timeline for the completion of those tasks. Delays in partial fulfillment do not waive the obligations of the party to meet the full terms of the agreement.

Delay due to unforeseen circumstances clause

This variation applies when a delay is caused by unforeseen circumstances.

If either party is delayed in fulfilling any request or obligation due to unforeseen circumstances outside of their control, the affected party shall promptly notify the other party in writing. The notification will include the reason for the delay and an updated timeline for fulfilling the obligation.

Delay in delivery clause

This variation applies when delays occur in the delivery of goods or services.

In the event of a delay in the delivery of goods or services, the party responsible for the delay will notify the other party as soon as possible. The delay must not exceed [X] days, and the party responsible for the delay will take all reasonable steps to ensure timely delivery moving forward.

Mutual delay clause

This variation applies when both parties experience delays.

If both parties encounter delays in fulfilling their respective obligations under this agreement, both parties agree to extend the performance timelines mutually, in writing, for a period that reflects the delays experienced by both parties. Such an extension will be negotiated in good faith to ensure continued cooperation.

Delay due to resource unavailability clause

This variation applies when delays arise from the unavailability of necessary resources.

If a party experiences a delay due to the unavailability of critical resources necessary to fulfill their obligations under this agreement, the party must immediately inform the other party. A new timeline for performance will be agreed upon based on the availability of those resources.

Delay in approval process clause

This variation applies when delays are caused by the approval process.

Any delay caused by the approval process of documents or deliverables shall be communicated promptly. Both parties agree to allow a reasonable period for the approval process and may mutually agree to adjust deadlines accordingly.

Delay in scheduling clause

This variation applies when delays occur due to scheduling issues.

If a party is delayed due to scheduling conflicts or delays in coordinating with necessary stakeholders, they shall notify the other party promptly. A rescheduled timeline will be agreed upon to ensure that all obligations are completed in a timely manner.

Delay in project milestones clause

This variation applies when delays occur in achieving project milestones.

If any project milestone is delayed, the affected party shall provide written notice, including the reason for the delay, and propose a revised timeline for completion. Both parties will cooperate to adjust subsequent milestones as needed to accommodate the delay.

Delay due to weather conditions clause

This variation applies when weather conditions cause a delay.

If a delay occurs due to adverse weather conditions, the affected party will notify the other party immediately. Both parties agree to extend the timeline as necessary and may agree on alternative arrangements to minimize the impact of the delay.

Delay due to technical issues clause

This variation applies when technical issues cause a delay.

In the event that technical issues delay the fulfillment of obligations under this agreement, the affected party shall promptly notify the other party and provide a reasonable estimate of when the issue will be resolved. Both parties will discuss possible adjustments to timelines to mitigate the effects of the delay.

Delay in regulatory approval clause

This variation applies when delays are caused by regulatory approval processes.

If a delay is caused by the need for regulatory approval, the affected party agrees to inform the other party as soon as the delay is known. The parties will work together to navigate the approval process and adjust timelines accordingly.

Delay in third-party deliverables clause

This variation applies when delays occur due to third-party deliverables.

If a delay in fulfilling obligations occurs because of third-party deliverables, the affected party will notify the other party in writing. The party responsible for engaging the third party will take all reasonable measures to expedite the third-party's performance and keep the other party updated on progress.

Delay due to workforce issues clause

This variation applies when workforce issues cause a delay.

If a delay arises due to issues with workforce availability, such as labor strikes or employee shortages, the affected party must notify the other party promptly. A revised timeline for performance will be agreed upon, and both parties will cooperate to resolve any workforce-related challenges.

Delay due to supply chain disruptions clause

This variation applies when supply chain disruptions cause delays.

If a delay occurs due to disruptions in the supply chain, the affected party will inform the other party immediately. Both parties will work together to find solutions, such as sourcing alternative suppliers, and will agree on a revised delivery schedule.

Delay in completion of work clause

This variation applies when there is a delay in completing the work.

If the completion of work under this agreement is delayed, the party responsible for the delay must notify the other party and provide a new completion date. Both parties will agree to an extension or adjustment to the timeline as needed to accommodate the delay.

Delay due to technical review clause

This variation applies when delays occur due to a technical review process.

If a delay is caused by the need for a technical review, the affected party shall inform the other party of the delay. Both parties will mutually agree on a reasonable period for the review and any necessary adjustments to deadlines.

Delay in approvals or sign-offs clause

This variation applies when delays occur due to approvals or sign-offs from stakeholders.

If a delay is caused by a delay in approvals or sign-offs from stakeholders, the responsible party shall promptly notify the other party. The parties will mutually agree on a revised timeline to accommodate the approval process.

Delay in regulatory filings clause

This variation applies when a delay is caused by regulatory filings.

If any regulatory filings necessary for this agreement are delayed, the party responsible for the filing shall inform the other party. Both parties will agree on a revised timeline to complete the filing and proceed with the agreement's obligations.

Delay in final deliverables clause

This variation applies when delays affect the final deliverables.

If there is a delay in the submission or delivery of final deliverables under this agreement, the responsible party will notify the other party immediately. The parties will adjust the timeline for final deliverables to ensure completion within a mutually agreed period.

Delay caused by force majeure events clause

This variation applies when force majeure events delay fulfillment.

In the event of a force majeure event, such as a natural disaster or political unrest, that causes a delay in fulfilling any obligations under this agreement, the affected party will notify the other party promptly and seek a reasonable extension of the deadline based on the duration of the force majeure event.

Delay in payment processing clause

This variation applies when delays occur due to payment processing issues.

If a delay in payment processing causes a delay in the fulfillment of any obligations under this agreement, the responsible party will notify the other party immediately and provide an updated payment schedule to ensure that work can continue.

Delay due to resource constraints clause

This variation applies when a delay occurs due to resource constraints.

If a delay occurs because of resource constraints, including limited availability of personnel, materials, or equipment, the affected party will notify the other party and propose a revised schedule to complete the obligations under this agreement.

Notification of delays clause

This variation applies when requiring notification for any delays.

If a delay occurs in fulfilling any request or obligation under this agreement, the party experiencing the delay must notify the other party in writing within [X] days, outlining the reason for the delay and the estimated duration of the delay.

Delay in contractual milestones clause

This variation applies when delays affect contractual milestones.

If any milestone or deadline is delayed, the party responsible for the delay must notify the other party and propose a new completion date. The parties will agree to extend subsequent milestones to ensure that the project remains on track.

Delay in document submission clause

This variation applies when delays occur in the submission of documents.

If there is a delay in submitting any documents required under this agreement, the party responsible for the delay must inform the other party and provide a new submission deadline. The parties will work together to ensure that documents are submitted promptly.

Delay in testing or evaluation clause

This variation applies when delays occur in testing or evaluation processes.

If there is a delay in the testing or evaluation of goods or services under this agreement, the party responsible for the delay must notify the other party immediately. The parties will agree to an updated timeline for completing the testing or evaluation process.

Delay in project delivery clause

This variation applies when the delivery of the project is delayed.

If the completion or delivery of the project is delayed for any reason, the responsible party must provide a written notice detailing the cause of the delay. Both parties will agree on a revised project delivery timeline to ensure the successful completion of the project.

Delay in providing services clause

This variation applies when there is a delay in providing services.

If there is a delay in providing any services as outlined in this agreement, the responsible party shall inform the other party in writing as soon as possible. The affected party will propose a new service delivery date, and both parties will work together to ensure the continued progress of the agreement.

Delay in performance milestones clause

This variation applies when delays affect performance milestones.

If any performance milestones are delayed, the responsible party shall notify the other party and propose a new deadline for the milestone. Both parties will discuss and agree on any necessary adjustments to the timeline to ensure that the obligations are ultimately fulfilled.

Delay due to logistical issues clause

This variation applies when logistical issues cause a delay.

If a delay occurs due to logistical issues, such as shipping delays, customs clearance, or transportation problems, the party responsible for the delay must notify the other party immediately and provide a revised schedule for fulfillment of obligations under the agreement.

This variation applies when delays occur due to legal approval processes.

If any delay arises due to the need for legal approvals or regulatory clearance, the affected party must notify the other party as soon as possible. The parties will agree to extend timelines as necessary and take appropriate action to expedite the approval process.

Delay in delivery of materials clause

This variation applies when delays are caused by the late delivery of materials.

If the timely delivery of materials is delayed by one party, they must notify the other party immediately. The responsible party will outline a new delivery schedule, and any delays will not affect the other party’s performance under the agreement.

Delay in final report submission clause

This variation applies when delays affect the submission of final reports.

If the final report or deliverable is delayed, the party responsible for the delay must provide a written explanation for the delay and submit a revised delivery date. Both parties will adjust the schedule accordingly to reflect the new timeline for submission.

Delay in authorization process clause

This variation applies when delays occur due to the authorization process.

If any delay is caused by delays in obtaining necessary authorizations or approvals from the relevant authorities, the affected party shall notify the other party as soon as possible and provide an updated timeline for the completion of the required authorizations.

Delay due to contractor delays clause

This variation applies when delays occur due to contractor performance.

If any delay occurs due to a subcontractor or contractor not fulfilling their obligations under this agreement, the responsible party will inform the other party and take all reasonable steps to rectify the issue promptly. The affected party will work to establish a new timeline with the responsible party.

Delay due to design changes clause

This variation applies when delays occur due to changes in design.

If there is a delay due to changes in design, the party requesting the changes must inform the other party and negotiate a new completion date for the modified deliverables. The parties agree to work collaboratively to minimize any disruption caused by design changes.

Delay in confirmation of terms clause

This variation applies when delays are caused by the time it takes to confirm terms.

If there is a delay in confirming the final terms of the agreement or any modifications, the party responsible for the delay will notify the other party. The parties will extend the timeline accordingly to allow for the completion of necessary confirmations.

Delay due to technical review clause

This variation applies when delays are caused by the need for technical review.

If a delay occurs because of the time needed for technical review or approval of deliverables, the party responsible for the delay must inform the other party in writing. Both parties will agree to extend deadlines based on the time required for review and adjustments.

Delay due to unforeseen supplier issues clause

This variation applies when delays occur due to supplier-related issues.

If a delay arises due to issues with suppliers, the affected party shall notify the other party promptly and provide an updated timeline. The responsible party agrees to take all reasonable measures to address supplier delays and minimize the impact on the overall timeline.

Delay in installation clause

This variation applies when delays are caused by installation processes.

If the installation of goods or services is delayed, the responsible party will notify the other party immediately and provide a new installation schedule. The delay will be accounted for, and both parties will adjust their performance deadlines accordingly.

Delay due to shortage of materials clause

This variation applies when delays occur due to a shortage of materials.

If a delay occurs because of a shortage in materials necessary for fulfilling the obligations of this agreement, the responsible party must notify the other party immediately and propose a new timeline for completing the task or delivering the product.

Delay in regulatory compliance clause

This variation applies when delays are caused by regulatory compliance issues.

If a delay is caused by the failure to meet regulatory requirements or obtain necessary regulatory approvals, the responsible party shall inform the other party immediately and provide a revised timeline for compliance.

Delay in providing feedback clause

This variation applies when delays are caused by the time needed to provide feedback.

If there is a delay in providing feedback or approval on deliverables, the requesting party shall notify the other party of the delay and specify the expected feedback timeline. Both parties will agree to adjust deadlines as needed to account for the delay.

This variation applies when delays are caused by legal disputes.

In the event of a legal dispute that impacts the performance of this agreement, the affected party will notify the other party and provide a revised timeline for fulfilling obligations once the dispute has been resolved.

Delay due to equipment malfunction clause

This variation applies when delays occur due to equipment issues.

If a delay occurs due to equipment malfunction or failure, the affected party will notify the other party immediately and provide an estimated timeline for resolving the issue. Both parties will work together to address the delay and minimize any disruptions to the agreement.

Delay in testing results clause

This variation applies when delays occur due to the delay in receiving testing results.

If the results of required testing are delayed, the party responsible for providing the results will inform the other party of the delay and provide a new expected delivery date for the results.

Delay in completing documentation clause

This variation applies when there is a delay in completing documentation.

If a delay occurs in completing necessary documentation under this agreement, the responsible party shall notify the other party immediately and provide a revised timeline for the completion and submission of such documentation.

Delay in implementing changes clause

This variation applies when delays occur due to the implementation of changes.

If changes to the project scope or deliverables are requested and cause delays, the requesting party will notify the other party of the delay and propose a revised timeline for the completion of the modified deliverables.

Delay in project initiation clause

This variation applies when delays affect the initiation of a project.

If there is a delay in the initiation of the project due to unforeseen circumstances or lack of readiness, the responsible party must notify the other party promptly and agree on a new start date for the project.

Delay in obtaining necessary permits clause

This variation applies when delays occur due to permit acquisition.

If a delay arises due to the failure to obtain necessary permits or licenses required for the performance of the agreement, the affected party shall notify the other party immediately and provide an updated timeline once the permits are obtained.

Delay in shipping clause

This variation applies when delays occur in the shipping process.

If a delay arises due to shipping issues, such as delays in transportation, the party responsible for shipping must notify the other party as soon as possible. A new delivery date will be agreed upon based on the revised shipping timeline.

Delay due to customer approval clause

This variation applies when delays occur due to customer approval.

If the delay occurs because the customer has not provided necessary approvals or feedback in a timely manner, the responsible party will notify the other party and extend deadlines accordingly based on the time required for the customer’s response.

Delay in warranty claims clause

This variation applies when delays occur in addressing warranty claims.

If a delay occurs due to the resolution of warranty claims, the responsible party will notify the other party and provide an updated timeline for fulfilling warranty obligations under this agreement.

Delay due to internal review clause

This variation applies when a delay occurs due to internal review processes.

If a delay arises due to the need for internal review or internal approval processes, the party responsible for the delay will notify the other party and provide a new timeline for completing the required review and obtaining approval.

Delay in obtaining financing clause

This variation applies when delays are caused by obtaining financing.

If a delay occurs due to the time required to secure financing necessary for the performance of this agreement, the responsible party will notify the other party promptly and work together to establish a revised timeline for fulfilling obligations under the agreement.

Delay due to unexpected demand clause

This variation applies when delays are caused by unexpectedly high demand.

If a delay occurs due to unexpected demand for products or services outlined in this agreement, the affected party will notify the other party immediately and propose a new timeline based on the increased demand.

Delay in obtaining resources clause

This variation applies when delays occur due to a lack of resources.

If a delay occurs due to the unavailability of necessary resources (personnel, equipment, etc.), the affected party must notify the other party and propose a new timeline for completing the obligations under the agreement.

Delay in contract execution clause

This variation applies when delays occur in the execution of the contract itself.

If there is a delay in executing this agreement or completing any preliminary steps, the responsible party will notify the other party and propose a new timeline for finalizing the contract or beginning the performance of the contract obligations.

Delay due to political instability clause

This variation applies when delays are caused by political instability.

If a delay occurs due to political instability or government intervention, the affected party will notify the other party promptly. A new timeline for performance will be agreed upon, considering the impact of political factors on the agreement.

Delay in verification process clause

This variation applies when delays occur in the verification of deliverables or services.

If a delay occurs due to the verification process of deliverables or services under this agreement, the responsible party will notify the other party of the delay and provide a new timeline for completing the verification process.

This variation applies when delays are caused by legal clearance.

If a delay occurs due to the time required to obtain legal clearance or approval for certain aspects of this agreement, the responsible party will notify the other party immediately and provide a revised timeline for the completion of such clearance processes.

Delay due to unforeseen technical issues clause

This variation applies when delays occur due to unforeseen technical issues.

If the performance of obligations is delayed due to unforeseen technical issues or system failures, the affected party shall immediately notify the other party and provide a revised timeline for completion once the technical issues have been resolved.

Delay in project approval clause

This variation applies when delays occur due to the need for project approval.

If there is a delay in obtaining necessary approvals for a project under this agreement, the responsible party will inform the other party and provide a new schedule for when the approval is expected to be granted and the work can proceed.

Delay due to pending regulatory review clause

This variation applies when delays arise due to pending regulatory reviews.

If any delay arises due to a pending regulatory review or investigation, the affected party will notify the other party immediately and propose a new timeline once the regulatory approval process has been completed.

Delay in system integration clause

This variation applies when delays occur in system integration.

If a delay arises due to the integration of systems or technologies under this agreement, the responsible party will notify the other party and provide a revised timeline based on the current progress of the integration.

This variation applies when delays occur due to the need for third-party consent.

If a delay occurs because the consent or approval of a third party is required before performance can proceed, the responsible party shall inform the other party of the delay and provide a new timeline based on the expected timing of obtaining consent.

Delay in resource allocation clause

This variation applies when delays arise due to resource allocation issues.

If there is a delay due to the unavailability or reallocation of necessary resources, the responsible party will notify the other party immediately and propose a new schedule for fulfilling their obligations under this agreement.

Delay in service activation clause

This variation applies when delays occur in activating a service.

If the activation of any service under this agreement is delayed, the responsible party shall inform the other party of the delay and provide a new service activation date. Both parties will agree on an extension for the completion of all related obligations.

Delay in delivering final product clause

This variation applies when delays affect the delivery of the final product.

If the final product is delayed, the responsible party shall notify the other party and provide a new delivery date. Both parties will work together to ensure that the delay does not affect the overall progress of the agreement.

Delay due to administrative processing clause

This variation applies when delays occur due to administrative processes.

If any delay arises due to administrative processes or internal approvals required by either party, the responsible party shall notify the other party promptly and provide an updated timeline for the completion of the process.

Delay in vendor delivery clause

This variation applies when delays occur due to vendor performance.

If a vendor delays the delivery of materials or services required under this agreement, the affected party shall inform the other party and provide a revised timeline for delivery based on the vendor's new schedule.

Delay in payment processing clause

This variation applies when delays occur in payment processing.

If a delay in payment processing occurs, the responsible party must notify the other party immediately and propose a revised payment schedule. Any delays will not affect the performance of obligations unless otherwise agreed.

Delay due to unexpected demand clause

This variation applies when delays occur due to unexpected demand.

If an unexpected increase in demand causes a delay in fulfilling the terms of this agreement, the responsible party will notify the other party and provide an updated timeline reflecting the impact of increased demand on fulfillment.

Delay in contract negotiation clause

This variation applies when delays arise during contract negotiations.

If a delay occurs due to extended negotiations or the time required to finalize the terms of the agreement, the responsible party will inform the other party and propose an updated timeline for concluding the agreement.

Delay in providing documentation clause

This variation applies when there is a delay in providing required documentation.

If any required documentation is delayed, the party responsible for providing it must notify the other party and provide a revised submission timeline. Delays in documentation will not release either party from their obligations under the agreement.

Delay due to personnel issues clause

This variation applies when delays are caused by personnel issues, such as illness or unavailability.

If a delay arises due to personnel issues, such as illness or unavailability of key team members, the affected party shall notify the other party promptly and provide a revised schedule for completing the relevant tasks.

This variation applies when delays occur due to the processing of legal documentation.

If there is a delay in processing legal documents or completing legal procedures required under this agreement, the responsible party will notify the other party and provide an updated timeline for completing the necessary processes.

Delay due to non-availability of key decision-makers clause

This variation applies when delays are caused by the unavailability of key decision-makers.

If delays occur due to the unavailability of key decision-makers who are required to make decisions for the progression of this agreement, the responsible party will notify the other party and propose a new decision-making timeline.

Delay in product development clause

This variation applies when delays arise in product development.

If the product development process is delayed, the responsible party will promptly notify the other party and provide a new timeline for the completion of product development milestones.

Delay due to delays in product inspection clause

This variation applies when delays occur due to product inspections.

If there is a delay in the completion of product inspections or testing required for the acceptance of deliverables, the affected party will notify the other party and provide a new inspection schedule.

Delay in regulatory certification clause

This variation applies when delays are caused by regulatory certification requirements.

If a delay is caused by the time needed to obtain necessary regulatory certifications for products or services under this agreement, the responsible party must notify the other party immediately and provide an updated timeline for certification approval.

Delay in finalizing project scope clause

This variation applies when delays occur due to the finalization of the project scope.

If the project scope is delayed due to the time required for finalizing project details or specifications, the responsible party will notify the other party of the delay and propose a revised timeline for completion.

Delay due to conflicting priorities clause

This variation applies when delays arise due to conflicting priorities.

If either party experiences a delay due to competing priorities or resource conflicts, they shall notify the other party promptly. A new timeline will be agreed upon that allows for the successful completion of the affected tasks.

Delay due to shipping carrier issues clause

This variation applies when shipping carrier issues cause a delay.

If a delay arises due to issues with the shipping carrier, such as delays in transit or customs processing, the responsible party shall notify the other party and provide a revised shipping and delivery schedule.

Delay in providing required approvals clause

This variation applies when delays occur due to required approvals not being provided on time.

If any required approvals are delayed, the party responsible for providing such approvals must notify the other party and outline an updated timeline for providing the necessary approvals.

Delay in supply chain disruptions clause

This variation applies when delays occur due to supply chain disruptions.

If a supply chain disruption causes a delay in fulfilling any part of this agreement, the affected party will notify the other party promptly and provide a revised timeline for fulfillment based on the updated supply chain conditions.

Delay in executing payment schedule clause

This variation applies when delays occur in executing the payment schedule.

If there is a delay in executing the agreed-upon payment schedule, the responsible party will notify the other party and provide an updated payment schedule. Failure to adhere to the payment schedule may result in penalties or the suspension of services.

Delay in resolving internal conflicts clause

This variation applies when delays occur due to internal conflicts.

If a delay arises due to internal conflicts or disagreements within either party, they must notify the other party promptly and provide an updated timeline for resolving the conflict and continuing performance under the agreement.

Delay in product customization clause

This variation applies when delays occur due to the customization of products.

If a product customization is delayed, the responsible party will notify the other party immediately and provide a revised delivery schedule for the customized product or service.

Delay in service completion clause

This variation applies when delays occur in completing services under the agreement.

If the completion of services is delayed, the party responsible for the delay must notify the other party and propose a new completion date. The delay will not release the delaying party from their contractual obligations.

Delay due to internal approval processes clause

This variation applies when internal approval processes cause a delay.

If any delay occurs due to the time required for internal approvals or decision-making processes within either party, the responsible party shall inform the other party and provide an updated timeline for completing the necessary approvals.

Delay in providing necessary tools clause

This variation applies when delays are caused by a lack of necessary tools or resources.

If a delay occurs due to the lack of necessary tools or resources needed to perform obligations under this agreement, the responsible party will notify the other party promptly and provide a new timeline once the required resources are available.

Delay due to delays in final testing clause

This variation applies when delays occur due to final testing of products or services.

If the final testing or quality assurance process is delayed, the responsible party will notify the other party and provide a revised testing schedule to ensure that the necessary tests are completed before final delivery.

Delay due to contractor availability clause

This variation applies when delays are caused by contractor availability.

If a contractor or subcontractor’s unavailability causes a delay, the responsible party will notify the other party and provide a new timeline for the completion of work, including steps taken to secure alternate resources.

Delay due to approval of specifications clause

This variation applies when delays arise from the approval of specifications.

If delays occur due to the time needed to approve project specifications, the responsible party shall notify the other party immediately and provide an updated approval timeline for the specifications. Both parties will cooperate to ensure timely approval.

This article contains general legal information and does not contain legal advice. Cobrief is not a law firm or a substitute for an attorney or law firm. The law is complex and changes often. For legal advice, please ask a lawyer.